CLOUDS ON THE RANGE
Data Centers & Agriculture

Prineville Data Centers and Infrastructure

What the public record shows about data center growth, groundwater, electricity infrastructure, agriculture and the questions that still remain in Central Oregon.

What we know so far

The scale is bigger than it looks from the road. The City’s January 2025 Economic Opportunities Analysis describes Meta’s campus at roughly 375 acres with 11 data-center buildings, and Apple’s at roughly 364 acres with three buildings constructed and three approved, through 2024.Prineville changed its urban growth boundary six times between 2012 and 2017, primarily to accommodate data-center development and expansion. That makes this a city-planning story as well as a campus story.The acreage already includes some parking, drainage, utilities, substations and expansion areas. Off-site corridors and shared systems need separate mapping to avoid counting the same land twice. These dated planning figures are not a current inventory of operating buildings or a measurement of farmland lost.The records below follow that physical growth alongside a transmission proposal, water projects and Apple’s tax and project-fee arrangements. The main unresolved question is how the facilities connect to shared systems and their costs.City Economic Opportunities Analysis, printed pages 1 and 39

Electricity infrastructure

Pacific Power’s October 2018 CU-2018-105 application describes proposed transmission work involving the Corral, Friend, Ochoco and Ponderosa substations. It also references a second phase with two triple-circuit 230/230/115-kV lines between Friend and Ochoco.That application establishes what was proposed. It does not, on its own, establish which components were completed, which campus required them or how the final costs were divided. The timing overlaps with data-center expansion, but timing alone cannot assign a project to Meta or Apple.Pacific Power CU-2018-105 application, October 2018Apple’s renewable-energy accountApple’s July 2020 announcement identifies Oregon’s 200-megawatt Montague wind farm as a project powering its Prineville data center. This is an operator statement about a renewable-energy project. The 200 MW figure is not a measurement of the campus’s instantaneous electricity demand, and it does not establish the complete supply mix or physical transmission route.Apple’s July 2020 announcementThe remaining electricity questions concern campus service and cost allocation: which upgrades served which customers, capacity added, construction contributions, tariff obligations and costs retained by the utility. Renewable-energy procurement does not answer those questions by itself.Oregon PUC: Large Customer Demand

Reading the infrastructure record

A planning approval, a utility application and a payment record answer different questions. I keep the project, operator, date and evidence type attached to each finding.A transmission proposal shows planned work. A tax resolution shows an approved obligation. A company announcement describes the company’s account. Connecting those records requires site-specific evidence; timing and proximity alone cannot establish who needed an upgrade or ultimately paid for it.

Water and public obligations

Water and reusePrineville’s wastewater history and Crooked River Wetlands Complex document a municipal treatment-and-reuse system. Those citywide records do not establish that reclaimed water supplies Meta or Apple’s cooling systems. Campus sources, reuse volumes and discharge routes need their own records.City of Prineville: Crooked River Wetlands ComplexStoring water for later useIn December 2018, Prineville announced that Apple would fund an $8.7 million aquifer storage and recovery project. The project was intended to store water underground for later use and improve seasonal water availability.Correction, October 20, 2026: An earlier version described the announced funding as a completed contribution.Apple’s tax and project-fee agreementsResolution 1184 approved a 15-year enterprise-zone property-tax exemption for an Apple facility in April 2012. It does not establish the exemption years for every later building.Resolution 1299, adopted August 9, 2016, records the $150,000 annual project fee under the 2012 agreement and a February 2016 agreement for additional Apple property. Its attached amendment divides the first $150,000 of combined annual fees equally between City and County for 2016–2027. Amounts above that threshold, and fees received after 2027 under the 2016 agreement, are allocated 80% to County and 20% to City.These are obligations and distribution terms. Receipts, exempt values and the full cost of campus service require separate accounting.Resolution 1184 · Resolution 1299 and attached Amendment No. 1

What happened when

2011
Meta says its first custom-built Prineville data center opens. Construction beginning in 2010 is a separate event.
2012–2017
Six urban growth boundary changes primarily accommodate data-center development and expansion. The sequence includes 96 and 114 acres for Apple, 160 acres near the airport where the proposed data-center development did not proceed, and 38 acres for Meta in 2017.
2012 and 2016
City resolutions document Apple’s exemption approval, later property agreement and project-fee distribution terms.
2018
Pacific Power submits the transmission-capacity application. The City announces the Apple-funded ASR project. These are a proposal and a funding announcement, respectively.
Through 2024
The January 2025 EOA describes Meta’s roughly 375-acre campus and Apple’s roughly 364-acre campus, including some supporting infrastructure and expansion land. See the opening for building counts and the source.
January 2025 Economic Opportunities Analysis · Meta’s 2018 opening account

Stewardship and remaining questions

Stewardship and campus water useApple’s April 2024 announcement says its Prineville data center obtained Alliance for Water Stewardship certification in 2021. The certificate boundary, audit and campus water balance are needed to assess its scope. The operator’s announcement does not supply those records.Apple’s water-stewardship announcementWhat remains unresolvedThe main gaps are campus-specific water source, use, cooling and discharge; which electric upgrades served which customers and how costs were allocated; and complete tax agreements, compliance and payment history.The reviewed evidence does not establish that data-center operations caused private-well contamination or agricultural harm. The separate well investigation needs an official source finding before it can be connected to these campuses. Producer observations and measured effects require the same care.

Sources & primary records

Most of what I am using for Prineville comes from city planning records, utility filings and state documents.The city records are especially useful because they show how the data centers changed the physical map of Prineville over time.City of PrinevilleThe city's Economic Opportunities Analysis is one of the most useful records so far. It lays out the growth of the Meta and Apple campuses, the number of buildings, acreage and the history of urban growth boundary changes tied to data center development.City of Prineville Economic Opportunities AnalysisCity wastewater records also help explain Prineville's long history of reclaimed water use and the infrastructure built around wastewater treatment and reuse.City of Prineville Wastewater System HistoryThe Crooked River Wetlands Complex is another piece of that system.City of Prineville: Crooked River Wetlands ComplexPacific PowerTransmission and land use records help show how the electrical system around Prineville changed as large industrial loads grew.One of the records I am using describes transmission work involving the Corral, Friend, Ochoco and Ponderosa substations.Pacific Power transmission project land use applicationOregon Public Utility CommissionThe PUC is useful for understanding the broader question of how Oregon utilities handle very large electrical loads and who is expected to pay for new infrastructure.Oregon PUC: Large Customer DemandOregon Health Authority and state groundwater recordsThe linked June 11, 2026 OHA notice concerns contaminants in private wells north of Prineville; it is separate from a finding about data-center causation.Those records are important context, but I am keeping that investigation separate from the data center story unless the evidence gives us a reason to connect them.Oregon Health Authority: Crook County Well InvestigationI am still looking for the records that answer the harder questions.Facility-level water use.Electrical capacity added for Meta and Apple.Who paid for specific transmission and substation projects.Parcel history before the campuses expanded.And the infrastructure sitting outside the property lines that does not show up when you only count the acreage of the data centers themselves.As those records come in, I will add them here and update the page.The Economic Opportunities Analysis is dated January 2025 and appears in the February 18, 2025 Planning Commission packet. See printed pages 1 and 39 for boundary changes and campus totals.Meta’s account of its 2011 openingApple tax and project-fee recordsCity Resolution 1184, April 2012: approval of a 15-year exemption for an Apple facility.City Resolution 1299 and attached amendment, August 2016: fee and distribution terms. These do not replace payment records or complete exemption agreements.Aquifer storage announcementCity of Prineville and Apple Partner to Create Long-Term Water Supply Solution, December 19, 2018. Historical City announcement identifying Apple as funding an $8.7 million project. The former City PDF address returned a missing-page error during this review, so no working original download is represented here. The announcement is not final cost or payment accounting.Operator statementsApple’s April 2024 water-stewardship announcement and July 2020 renewable-energy announcement. These support attributed company statements; certification scope, measured campus demand and physical electricity service need separate evidence.Browse the full Sources page · Get the free community guide

About this case study

I follow how data-center development changes land use and shared infrastructure in an agricultural region. I keep planning records, company statements and measured outcomes distinct, and update the page when evidence changes the account.Reviewed October 20, 2026. Campus figures describe development through 2024. Proposal, funding-announcement and payment limits remain in the relevant sections. The 2011 opening and ASR-funding corrections are retained.Clouds on the Range is an independent research project examining data centers, agriculture, water, energy, infrastructure and rural communities.